PROJ 1002-AF Project 2
0 Download5 Pages / 1,242 Words
Course Code: PROJ1002AF
University: Middle East College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Oman
Question:
You need to produce a project plan for a suitable project for your work-place (An Online Registration Project for an Educational Institute). The Project Plan will include the use of Project Management tools and techniques studied and discussed in the class. You will need to submit the project plan with clear indication of your contributions.
You should include the following:
Project Introduction and Objectives
Project team and their roles;
Answer:
Project Introduction and Objectives
The purpose of this project is to develop an online registration system for the educational institute that would allow students the register themselves with the institute online for particular courses. The system would first be developed separately as a standalone code and then it would be integrated with the existing system of the school. Java would be used for the development of the system while MySQL would be used for managing database queries.
Project team and their roles
The project team would consist of following members with defined roles and responsibilities:
Project Sponsor:
Assess project viability and approve it for sponsorship
Approve and provide funds for project execution(Pearson, 2000)
Project Manager:
Development of a project management plan
Managing and controlling project deliverables
Selection and recruitment of project members from the staff or from outside as well as assignment of project tasks to each of them
Lead and manage the project team members
Define the project schedule and keep monitoring its progress to keep control over the schedule
Monitor and give progress report to key stakeholders from the upper management of the institute
Prepare a project charter and get the same approved from the project sponsor to get funds
Prepare a schedule for the project and keep monitoring it to establish control on timelines(Bright Hub Media, 2013).
Designer:
Develop architecture for the online registration system
Understand user requirements and develop an online registration system prototype
Analyst:
Analyse the project deliverables for its feasibility
Analyse the requirements of the project and come up with most appropriate resource plan
Developer:
Understand user requirements and prototype document to convert it into program
Develop the codes for the development of application
End Users:
Participate in requirement gathering
Participate in end use testing phase
Trainer:
Gather training requirement from the users
Deliver training to users of the online registration system
Develop usage guide for online students who would be using the system for registration(BIS, 2010)
Project stages and key deliverables
The project would have specific deliverables including:
Online Registration system development project WBS or Activity list
Gantt Chart for Schedule
Network Diagram
Critical Path Analysis
Project plan including risk analysis and software design
Quality plan
Documentations including:
Software Requirements Specification Document (SRS)
Code documentation
Prototype document
Testing documentation(Bright Hub Media, 2015)
Project time management
The projects starts on 24th April 2017 and finishes on 6th October 2017. It takes total duration of 120 days.
Activity List
1.0 Initiation
1.1 Requirement Gathering
1.1.1 Users
1.1.2 Other stakeholders
1.1.2.1 Teachers or trainers at institute
1.1.2.1 Webmaster
1.1.2.2 Project Owner
1.2 Project Scope Development
1.3 Contractual agreements
1.3.1 Developers
1.3.2 Licences
1.3.2.1 Hosting
1.3.2.2 CMS
2.0 Design and Development
2.1 Front end interface design
2.1.1 Administrator interface
2.1.2 Student Interface
2.3 Architecture development
2.3.1 java Web Layout Design
2.3.2 MySQL Database
2.3.2.1 Tables
2.3.2.2 Schema
2.4 Functional Module Development
2.4.1 Registration
2.4.2 Data Circulation
3.0 Documentation
3.1 SRS
3.2 Prototype
3.3 Code
3.4 Testing
4.0 Finalization
4.1 Testing
4.1.1 Quality Testing
4.1.2 Functional Testing
4.1.3 Unit Testing
4.2 Integration with existing systems
4.2.1 Integration
4.2.2 Integration testing
4.3 Client Acceptance
4.3.1 Final user acceptance testing
4.3.2 Deliverables acceptance
5. Project Closure
5.1 Installation
5.2 Training
5.2.1 Administrator
5.2.2 Webmaster
5.2.3 Users
5.3 Implementation
5.4 Closure documentation
5.5 Project signoff from sponsor (CDC, 2006)
Gantt chart
Network Diagram
Critical Path
The tasks which are highlighted in red are critical tasks. Since may tasks are performed in parallel, there are more than one critical path.
Budget
The total budget allotted for the online registration application development is $110,000 which would include costs of development, human resources, systems, etc (WSDOT, 2015).
Project Expenses
Budget
Resource Selection
$5,000
Software development
$25,000
Hardware
$15,000
Networking
$5,000
Project Team
$30,000
Administrative costs
$10,000
Training
$5,000
Other Costs
$5,000
Contingency
$10,000
(PMI, 2015)
Quality Plan
Quality plan would ensure that all the activities and processes required for development of a quality online registration system are completed. The plan defines how quality is managed; identify quality assurance activities, quality control activities, and quality standards (Lacaster University, 2006).
Specific quality assurance activities that would be carried out in the development project include:
Technical Review
Software testing
Imposing of development standards
Change Control
Software metrics(Project Management Institute , 2000)
Specific quality control activities that would be carried out in the development project include:
Monitor if key deliverables are met
Identify standards and assure that they are met
Ensure that all project requirements are met
Define schedule for quality control checks
Use specific standards of quality for online registration system development ensuring:
Desired quality of the code
Defined degree of separation between the content and its presentation
Use attributes that make accessibility easy for users
Application should be accessible on all user devices
Site management must include defined error pages, site favicon and URL management(Time is Ltd, 2015)
Risk Management
Risk management plan would involve identification of risks, understanding of probability of risks occurrence, assessment of impacts, and planning of response from prevention, reduction, acceptance, contingency, and transferring.
Risk
Probability
Impact
Response Plan
Developer leaving the project in between
Low
High
Prevention: Project manager must keep communicating with developer and also have employment terms such that the developer cannot leave the project without informing 15 days in advance such that when the notice is given, the project manager would immediately start the process of hiring new developer
Delays in Deliverables
Medium
Low to Moderate
Reduction: If there are delays happening because of resource shortages or other causes, the underlying cause can be determined or resolved or new resources could be deployed to reduce the delivery time for remaining deliverables such that the final delivery date of the project is not affected.
The developed application does not meet all the stakeholder requirements
Low
Moderate to High
Prevention: Involve all key stakeholders who could affect the output in the requirement gathering stage and ensure all requirements are listed in the SRS document without miss such that all the requirements are met by deliverables
Transfer: If a part of deliverable that is given by a contractor then the risk may be transferred to the contractor and a relieve or redevelopment of the code can be asked for
Cost Overrun
Medium
Moderate to High
Reduction: Project manager must keep monitoring the project against the cost limitations such that when expenses are found to be increasing beyond limits, specific control measures are taken to bring down the costs in the remaining duration of the project. In case the reduction in cost is not possible then project manager would take extra approval from the sponsor to receive more funds to proceed.
Conclusions
This document proposed development of an online registration system for the use of college which would allow students to enrol in various programs running in the institute online. The application would be made using Java with MySQL database programming. The paper identified the resource requirements, budget requirements and explained the risks management plan for the project.
References
BIS, 2010. How to organise, plan and control Projects, s.l.: BIS.
Bright Hub Media, 2013. 5 Leadership Secrets of Successful Project Managers. [Online] Available at: https://www.brighthubpm.com/resource-management/122821-five-leadership-secrets-of-successful-project-managers/
Bright Hub Media, 2015. Constructing Powerful Scope Statements. [Online] Available at: https://www.brighthubpm.com/project-planning/57950-example-and-evaluation-of-project-scope-statements/
CDC, 2006. CDC Unified Process Practices Guide: Projecct Charter, s.l.: CDC.
Lacaster University, 2006. Case Study of Successful Complex IT Projects, s.l.: THE BRITISH COMPUTER SOCIETY .
Pearson, 2000. Basic Skills for Project Managers, s.l.: Pearson Education.
PMI, 2015. Capturing the Value of PROJECT MANAGEMENT, s.l.: PMI.
Project Management Institute , 2000. A guide to the Project Management Book of Knowledge , s.l.: Project Management Institute .
Time is Ltd, 2015. Evaluating a Project. [Online] Available at: https://www.time-is-ltd.co.uk/Management/Promise/PMManual/Evaluating%20a%20Project.htm
WSDOT, 2015. Cost Estimating Manual for Projects , s.l.: Washington State Department of Transportation.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 5 pages
PAY 3 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2021). PROJ 1002-AF Project 2. Retrieved from https://myassignmenthelp.com/free-samples/proj1002af-project-2/online-registration-system-for-the-educational-institute.html.
“PROJ 1002-AF Project 2.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/proj1002af-project-2/online-registration-system-for-the-educational-institute.html.
My Assignment Help (2021) PROJ 1002-AF Project 2 [Online]. Available from: https://myassignmenthelp.com/free-samples/proj1002af-project-2/online-registration-system-for-the-educational-institute.html[Accessed 19 December 2021].
My Assignment Help. ‘PROJ 1002-AF Project 2’ (My Assignment Help, 2021)
My Assignment Help. PROJ 1002-AF Project 2 [Internet]. My Assignment Help. 2021 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/proj1002af-project-2/online-registration-system-for-the-educational-institute.html.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com offers an all-inclusive academic paper writing service online. Students in search of a one-stop solution to their paper writing stringencies will find this portal extremely useful. Our in-house writers are well-aware of the conventions needed to be followed while drafting academic lab reports, CPM homework papers, dissertations on clinical reasoning cycle, rhetorical analysis and more. The dedicated team of writers is committed to providing each solution on time, and at the cheapest industry price.
div#loaddata .card img {max-width: 100%;
}