PRM701 Project Management Principles

0 Download17 Pages / 4,068 Words

Course Code: PRM701
University: University Of The Science

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United States

Questions:
To enable you, as part of a team, to design and plan a new project for authorisation and define its scope. The planning process is an opportunity for you to demonstrate that you can interact effectively in leadership and/or subordinate project roles.
Product:
Preliminary Project Charter and Management Plan for “NOOSA CONVENTION AND PERFORMING ARTS CENTRE”
Criteria

Application of an advanced understanding of the project management body of knowledge, including recent developments.
Designing and planning of a new project for authorisation and definition of its scope. Participation in a project team to achieve project objectives and balance project constraints.
Presentation of professional written material utilising relevant literature and industry benchmarks.

ATTACHED FILES TO BE REFERRED:

AEC – Noosa Convention and Performing Arts Centre Pre Feasibility Review
CCIQ Noosa Convention and Cultural Centre Initiative Pre Feasibility Study
Council report – Review of proposal for Noosa Convention and Cultural Centre
Convention Centre – Council resolution.

 
Answers: 

BACKGROUND
The project is developed for forming the effective and improved construction activities for building convention and art centre for Noosa. The construction activities would result in forming the development of the art and convention centre for Noosa. The project would consider the location, construction, and operation of the Noosa Convention and Art Centre. The development of the centre would help the business organization for listing the development of the operations for the alignment of the operations. 
DRIVERS FOR THE PROJECT
The CCIQ has initiated the project pre-feasibility analysis for development of the building for Convention and Art Centre of the improved functional and development model. The Council of AEC Gropu Pvt. Ltd. has been undertaking the review for the CCIQ’s feasibility analysis of Noosa Convention and Art Centre. The Council has taken the decision for initiating the plan development for the implication of the effective and improved functional development.
PROJECT OBJECTIVES
The objectives of the project is aligned for ensuring that improved communication is aligned for listing the development of the activities of the operations. The objectives of project include,

To develop a project plan for listing the facilities of the effective construction activities
To develop the convention and art centre for the alignment of the specific activities
To form the development of successive alignment activities for the user specific operations

 
PROJECT CONCEPT
The project of construction of Noosa Convention and Art Centre is based on the implication of the project management principles and Information Technology development. The formation of the effective and improved construction activities would ensure that the required centre construction is built at the required location. The feasibility study is formed for installing the development of the improved activities.
ALIGNMENT TO BUSINESS OBJECTIVES
The business objectives for the deployment of the effective and improved communication are helpful for listing the deployment of the effective business operations. The alignment of the improved activities would allow the formation of the convention and art centre for Noosa. The use of the centre would be helpful for renting it and getting the total cost recovery for the project development. The site development is successive with the implementation of the effective development process. The business objective for Noosa is to increase the operating revenue of $2,481,339.00 so that it exceeds the operating expenditure of $4,166,251.00. The total earnings of the organization must be a positive expected value due to the project.
SCOPE MANAGEMENT
DELIVERABLES
The deliverables for the project of construction of Noosa Convention and Art Centre are arranged chronologically in the following table,

Serial No

Deliverable

End Date

D1

Procurement Documentation for the project

Wed 2/21/18

D2

Charter Documentation

Mon 2/26/18

D3

Project Initiation Documentation

Wed 2/28/18

D4

Project Scheduling

Fri 3/2/18

D5

Accumulating material resources and machineries

Fri 3/16/18

D6

Setting site office

Mon 4/2/18

D7

Excavating site foundations and elevator pit

Tue 5/1/18

D8

Windows and Doors are Constructed

Tue 6/5/18

D9

Drainage and Plumbing is done

Fri 6/22/18

D10

Partition of site for Convention and Art Centre

Wed 7/4/18

D11

Convention Section is carved out

Tue 7/10/18

D12

Art centre is carved out

Fri 7/27/18

D13

Fire Safety and First Aid is installed in abundance

Wed 8/22/18

D14

Final Furnishing of the Centre

Thu 8/30/18

D15

Convention and Art Centre is Inaugurated

Thu 9/13/18

BUSINESS HUB
The business hub for the project includes the development of the effective operational center for developing improved operations for the organization. The Noosa Convention and Art Center require the use of the supportive development factor. The deployment of the effective and improved functional analysis is helpful for the deployment of the sufficient integration model.
 
SCOPE INCLUSIONS
The project scope for the project of construction of Noosa Convention and Art Centre includes the following items,
Documents: Project Charter, Project Initiation, Procurement, Contractor Agreement, Final Report, and Approval Documentation
Works: Site construction (clearing, pillar works, cementing, leveling, and concreting), Infrastructure construction (walls, floors, window, doors, and roofs), Interior Construction (power line, electricity, paintings, furniture, fixtures, and other works), and final construction (medical kit installation and fire safety installation)
SCOPE EXCLUSIONS
The project of construction of Noosa Convention and Art Centre excludes the development of communication plan, risk management plan, and development of transportation activities. The project manager would not have to take care of the operations of the contractor and the alignment of the effective change management plan.
ASSOCIATED WORKS
The associated works of the project include the development of the office site at the location of the site for ensuring effective communication. The formation of the Noosa convection and art center would be helpful for listing the deployment of the construction activities. The allocation of the successive modification of the construction is dependent of the integration of the construction management with the principles of project management. The activity of applying for electricity power, external power for the construction works, alignment of the communication at the work site, and machinery management.
HANDOVER
The project handover would be done when the government officer would inspect and approve the project operations for the alignment of the effective and improved project integration activities. The formation of the supporting documentation would allow the formation of the effective and improved functional development modification. The handover of the projects would be supplied for forming the occasional development of the convention and art centre for Noosa.
PROJECT ASSUMPTIONS   
ASSUMPTIONS
The assumptions of the project of construction of Noosa Convention and Art Centre are,
Expected outcome of pre-feasibility study:
The pre-feasibility study for the project of construction of Noosa Convention and Art Centre would yield expected results for CCIQ.
Completion of construction:
The completion of the construction works for the Noosa Convention and Art Centre must be done in the expected time and duration.
Profit generation:
The business objective for Noosa is to increase the operating revenue of $2,481,339.00 so that it exceeds the operating expenditure of $4,166,251.00 for generating profit for the organization.
CONSTRAINTS
The constraints of the project of construction of Noosa Convention and Art Centre are,
Time: The time duration acts as the major constraints for the project since the project of construction of Noosa Convention and Art Centre is a construction project. The project is expected to complete in duration of 6-7 months of time.
Cost: The resource utilization is a feasibility analysis factor that also acts the constraint for the project of construction of Noosa Convention and Art Centre. The overall budget of the project must be confided to $200,000 so that the organization can overcome this amount in short period of time.
Construction Factors: Some factors like weather, quality of raw materials, machine performance, and skill of workers also act as the constraints of the project.
POTENTIAL ISSUES
The potential issues of the project of construction of Noosa Convention and Art Centre are,
Lack of construction materials: The raw materials like sand, brick, clay, cement, pillars, and concrete are the primary raw materials required for the project of construction. The lack of these raw materials results in forming the major issue in forming the improvement of the operations.
Delay in construction: The delay in project activity completion results in forming the management of the profound system development. The alignment of the operations had resulted in listing the number of resources and probability of occurrence of the issues.
OPPORTUNITIES
The opportunities of the project of construction of Noosa Convention and Art Centre are,
Integration of the principles: The integration of the principles of project management and construction activities would be implied for the development of the operations. The analysis of the operations and linking the development of the operations would be possible for listing the deployment of the activities.
Increase in revenue: The revenue generation of the activities would be helpful for listing the development of the effective development model. The modification of the operations would align the modification had aligned the operational development of the operations.
INTEGRATION MANAGEMENT
METHODOLOGY
The methodology for the integration management for the project of construction of Noosa Convention and Art Centre include the following 6 steps,
Step 1: Initiating- The initiation phase is helpful for starting the integration management for the project operations
Step 2: Planning- The planning phase lists out the required activities for the implementation of the integration management of the construction projects
Step 3: Executing- The execution of the project activities would help in implying the activities of the implementation management
Step 4: Monitoring and Controlling- The monitoring and controlling would imply the modification of the occasional activities of the project
Step 5: Closing- The closing phase is formed for forming the effective and improved closure checklist for the project
CHANGE CONTROL
The change control is developed for ensuring that the project of construction of Noosa Convention and Art Centre would imply expected project outcomes from the project. The implication of the change control is helpful for listing the development of the effective and improved functional changes in the project. The change control can be implied by the help of 7QC tools and Six Sigma implementation.
PERFORMANCE REPORTING
The performance reporting for the project of construction of Noosa Convention and Art Centre is based on the project progress evaluation report that is made for ensuring that project activities are being carried out successfully as expected.
AUDIT
Project audit is done for analyzing the monetary benefits of the project of construction of Noosa Convention and Art Centre for developing effective and improved outcomes of the project. The audit can be done by analyzing the resource usage document, NPV analysis, and progress checklist.
DEPENDENCIES
The project dependencies are analyzed by considering the project plan in form of methodology and the relation of the tasks are the dependency for the project plan. The project plan is developed following the traditional waterfall methodology and it would help in forming the project timeline.
TIME MANAGEMENT
SCHEDULE
The project schedule for the project of construction of Noosa Convention and Art Centre is shown in the table below,

WBS

Task Name

Duration

Start

Finish

0

NOOSA CONVENTION AND PERFORMING ARTS CENTRE

157 days

Thu 2/8/18

Fri 9/14/18

1

   Preliminary Study

10 days

Thu 2/8/18

Wed 2/21/18

1.1

      Preparing Submit Bond and Insurance Documents

3 days

Thu 2/8/18

Mon 2/12/18

M1

      Obtaining Approval for Proceeding and Building Permits

2 days

Tue 2/13/18

Wed 2/14/18

1.3

      Feasibility Analysis of the Construction Requirements

3 days

Thu 2/15/18

Mon 2/19/18

1.4

      Procurement Documentation for the project

2 days

Tue 2/20/18

Wed 2/21/18

2

   Project Initiation

8 days

Thu 2/22/18

Mon 3/5/18

M2

      Project Kickoff meeting

1 day

Thu 2/22/18

Thu 2/22/18

2.2

      Charter Documentation

2 days

Fri 2/23/18

Mon 2/26/18

2.3

      Project Initiation Documentation

2 days

Tue 2/27/18

Wed 2/28/18

2.4

      Project Scheduling

2 days

Thu 3/1/18

Fri 3/2/18

2.5

      Submission of documents

1 day

Mon 3/5/18

Mon 3/5/18

3

   Site Development

41 days

Tue 3/6/18

Tue 5/1/18

3.1

      Clearing site

4 days

Tue 3/6/18

Fri 3/9/18

M3

      Accumulating material resources and machineries

5 days

Mon 3/12/18

Fri 3/16/18

3.3

      Installing power source

6 days

Mon 3/19/18

Mon 3/26/18

3.4

      Setting site office

5 days

Tue 3/27/18

Mon 4/2/18

3.5

      Cutting and Filling land of site as required

7 days

Tue 4/3/18

Wed 4/11/18

3.6

      Storm Drainage and Exterior Fire line development

6 days

Thu 4/12/18

Thu 4/19/18

M4

      Construction foundation for the site

3 days

Fri 4/20/18

Tue 4/24/18

3.8

      Excavating site foundations and elevator pit

5 days

Wed 4/25/18

Tue 5/1/18

4

   Construction of Convention and Arts Centre

87 days

Wed 5/2/18

Thu 8/30/18

4.1

      Floor and Wall Construction

25 days

Wed 5/2/18

Tue 6/5/18

4.1.1

         Steel Pillars are eradicated

4 days

Wed 5/2/18

Mon 5/7/18

4.1.2

         Concrete and Brick Walls are developed

6 days

Tue 5/8/18

Tue 5/15/18

4.1.3

         Concrete Flooring

7 days

Wed 5/16/18

Thu 5/24/18

4.1.4

         Developing Roofs

5 days

Fri 5/25/18

Thu 5/31/18

M5

         Windows and Doors are Constructed

3 days

Fri 6/1/18

Tue 6/5/18

4.2

      Electricity and Drainage works

21 days

Wed 6/6/18

Wed 7/4/18

4.2.1

         Power lines and electric supply is installed

7 days

Wed 6/6/18

Thu 6/14/18

4.2.2

         Drainage and Plumbing is done

6 days

Fri 6/15/18

Fri 6/22/18

4.2.3

         Painting and Other Carpentry Works are done

5 days

Mon 6/25/18

Fri 6/29/18

M6

         Partition of site for Convention and Art Centre

3 days

Mon 7/2/18

Wed 7/4/18

4.3

      Convention Section Development

13 days

Thu 7/5/18

Mon 7/23/18

4.3.1

         Convention Section is carved out

4 days

Thu 7/5/18

Tue 7/10/18

4.3.2

         Seating Arrangements and Interior Works are done

5 days

Wed 7/11/18

Tue 7/17/18

4.3.3

         Necessary Furniture and fixtures are formed

4 days

Wed 7/18/18

Mon 7/23/18

4.4

      Art Section Development

13 days

Tue 7/24/18

Thu 8/9/18

4.4.1

         Art centre is carved out

4 days

Tue 7/24/18

Fri 7/27/18

4.4.2

         Interior is lavishly developed

5 days

Mon 7/30/18

Fri 8/3/18

4.4.3

         All required tools and art equipments are installed

4 days

Mon 8/6/18

Thu 8/9/18

4.5

      Other Installation

15 days

Fri 8/10/18

Thu 8/30/18

4.5.1

         Matching Furniture, Fixtures, and Drapes are made

4 days

Fri 8/10/18

Wed 8/15/18

4.5.2

         Fire Safety and First Aid is installed in abundance

5 days

Thu 8/16/18

Wed 8/22/18

M7

         Final Furnishing of the Centre

6 days

Thu 8/23/18

Thu 8/30/18

5

   Inspection and Approval

10 days

Fri 8/31/18

Thu 9/13/18

5.1

      Development of final completed project report

5 days

Fri 8/31/18

Thu 9/6/18

5.2

      Submission of reports

1 day

Fri 9/7/18

Fri 9/7/18

5.3

      Government Officer Inspection

1 day

Mon 9/10/18

Mon 9/10/18

M8

      Approval from the officer

2 days

Tue 9/11/18

Wed 9/12/18

5.5

      Convention and Art Centre is Inaugurated

1 day

Thu 9/13/18

Thu 9/13/18

M9

   Project is Closed

1 day

Fri 9/14/18

Fri 9/14/18

MILESTONES
The milestones for the project of constructing the Noosa Convention and Art Centre are given below,
M1. Approval for project initiation- 2 days- Tue 2/13/18-Wed 2/14/18
M2. Project Kickoff meeting- 1 day- Thu 2/22/18-Thu 2/22/18
M3. Accumulating material resources and machineries- 5 days- Mon 3/12/18-Fri 3/16/18
M4. Construction foundation for the site- 3 days- Fri 4/20/18-Tue 4/24/18
M5. Windows and Doors are Constructed- 3 days- Fri 6/1/18-Tue 6/5/18
M6. Partition of site for Convention and Art Centre- 3 days- Mon 7/2/18 -Wed 7/4/18
M7. Final Furnishing of the Centre- 6 days- Thu 8/23/18-Thu 8/30/18
M8. Approval from the officer- 2 days- Tue 9/11/18-Wed 9/12/18
M9. Project is Closed- 1 day- Fri 9/14/18 -Fri 9/14/18
 
COST MANAGEMENT
COST MANAGEMENT FRAMEWORK
The cost management framework that would be used for the project of constructing the Noosa Convention and Art Centre is TCM or total cost management framework. The total cost management framework can be divided into four major sections namely basic process of cost management, functional process of strategic asset management, functional processes of project control and enabling process of total cost management.
PROJECT BUDGET
The project budget comprise of using both material and human resources for the development of the final project deliverable. The project budget is developed for ensuring that the overall cost of the project should not exceed $200,000.00. The detailed cost budget is given below,

Resource Name

Type of Resource

Work

Standard Rate

Cost

Documenter

Human

128 hrs

$80.00/hr

$10,240.00

Project Manager

Human

80 hrs

$125.00/hr

$10,000.00

Analyst

Human

24 hrs

$70.00/hr

$1,680.00

Planner

Human

16 hrs

$75.00/hr

$1,200.00

Contractor

Human

248 hrs

$115.00/hr

$28,520.00

Electrical Engineer

Human

192 hrs

$120.00/hr

$23,040.00

Workers

Human

264 hrs

$105.00/hr

$27,720.00

Civil Engineer

Human

200 hrs

$120.00/hr

$24,000.00

Mason

Human

104 hrs

$85.00/hr

$8,840.00

Carpenter

Human

40 hrs

$90.00/hr

$3,600.00

Interior Developer

Human

32 hrs

$100.00/hr

$3,200.00

Officer

Human

24 hrs

$0.00/hr

$0.00

Site Clearing Equipments

Material

1

$640.00

$640.00

Power Cost

Material

1

$1,340.00

$1,340.00

Bricks

Material

1

$1,640.00

$1,640.00

Sand

Material

1

$1,390.00

$1,390.00

Cement

Material

1

$1,590.00

$1,590.00

Clay

Material

1

$1,500.00

$1,500.00

Mixer

Material

1

$600.00

$600.00

Site Excavating Machinery

Material

2

$830.00

$1,660.00

Drainage Pipes

Material

1

$1,300.00

$1,300.00

Fire Line

Material

1

$1,800.00

$1,800.00

Steel Pillars

Material

1

$3,100.00

$3,100.00

Flooring Tiles

Material

1

$1,800.00

$1,800.00

Roof

Material

1

$1,800.00

$1,800.00

Windows

Material

1

$1,600.00

$1,600.00

Doors

Material

1

$2,000.00

$2,000.00

Line wires

Material

1

$2,200.00

$2,200.00

Meter

Material

1

$1,300.00

$1,300.00

Board

Material

1

$700.00

$700.00

Paints

Material

1

$2,900.00

$2,900.00

Carpentry tools

Material

1

$2,300.00

$2,300.00

Seats and Tables

Material

1

$4,300.00

$4,300.00

Furniture and Fixtures

Material

2

$7,300.00

$14,600.00

Art Tools and Equipments

Material

1

$3,300.00

$3,300.00

Fire Extinguisher

Material

1

$1,500.00

$1,500.00

First Aid kits

Material

1

$1,100.00

$1,100.00

Total Budget

$200,000.00

 
SOURCE OF FUNDS
The source of the funds for the project of constructing the Noosa Convention and Art Centre is the investments by Commonwealth Funding Approval.
FINANCIAL FEASIBILITY OUTCOMES
The financial feasibility outcomes of the project is shown below,
HUMAN RESOURCE MANAGEMENT
ROLES

Resource Name

Roles

Documenter

   Preparing Submit Bond and Insurance Documents

   Procurement Documentation for the project

   Charter Documentation

   Project Initiation Documentation

   Submission of documents

   Development of final completed project report

   Submission of reports

Project Manager

   Obtaining Approval for Proceeding and Building Permits

   Project Kickoff meeting

   Accumulating material resources and machineries

   Convention and Art Centre is Inaugurated

   Project is Closed

Analyst

   Feasibility Analysis of the Construction Requirements

Planner

   Project Scheduling

Contractor

   Clearing site

   Setting site office

   Storm Drainage and Exterior Fire line development

   Seating Arrangements and Interior Works are done

   Interior is lavishly developed

   Final Furnishing of the Centre

Electrical Engineer

   Installing power source

   Power lines and electric supply is installed

   Fire Safety and First Aid is installed in abundance

   Final Furnishing of the Centre

Workers

   Cutting and Filling land of site as required

   Steel Pillars are eradicated

   Developing Roofs

   Windows and Doors are Constructed

   Necessary Furniture and fixtures are formed

   All required tools and art equipments are installed

   Drainage and Plubming is done

Civil Engineer

   Construction foundation for the site

   Excavating site foundations and elevator pit

   Convention Section is carved out

   Art centre is carved out

   Partition of site for Convention and Art Centre

   Final Furnishing of the Centre

Mason

   Concrete Flooring

   Concrete and Brick Walls are developed

Carpenter

   Painting and Other Carpentry Works are done

Interior Developer

   Matching Furniture, Fixtures, and Drapes are made

Officer

   Government Officer Inspection

   Approval from the officer

 
COMMUNICATIONS MANAGEMENT
INTRODUCTION
The communication management is implied for effective communication plans for forming the flow of information in the project among the project stakeholders.
CONSTRAINTS
The medium, time, and technical difficulty acts as the constraints for the communication process of the project.
STAKEHOLDER COMMUNICATIONS
Stakeholder communications is implied for forming the development of the improved activities and alignment of the operations for the development of transfer management.
PROJECT TEAM DIRECTORY
The project team directory is implied for forming the development and alignment of the operations for the effective management process.
PROCUREMENT AND CONTRACTS MANAGEMENT
PROCUREMENT MANAGEMENT
The procurement management for the project can be done by following the steps mentioned below,
Step 1- Identification of the needs
Step 2- Description of the process and reason analysis
Step 3- Assigning type of procurement
Step 4- Development of timing of procurement and owner of project
Step 5- Updating the status of the procurement
Step 6- Closing the procurement process
QUALITY MANAGEMENT
The quality management process can be implied using PDCA cycle and it would help in improving the quality of the construction activities for the project. The following diagram is helpful for the development of the final quality management process,
 
REFERENCES
Abdollahi, M., Arvan, M. and Razmi, J., 2015. An integrated approach for supplier portfolio selection: Lean or agile?. Expert Systems with Applications, 42(1), pp.679-690.
Abrahamsson, P., Salo, O., Ronkainen, J. and Warsta, J., 2017. Agile software development methods: Review and analysis. arXiv preprint arXiv:1709.08439.
Azizi, A., 2015. Evaluation improvement of production productivity performance using statistical process control, overall equipment efficiency, and autonomous maintenance. Procedia Manufacturing, 2, pp.186-190.
Balasubramanian, B.A., Cohen, D.J., Davis, M.M., Gunn, R., Dickinson, L.M., Miller, W.L., Crabtree, B.F. and Stange, K.C., 2015. Learning evaluation: blending quality improvement and implementation research methods to study healthcare innovations. Implementation Science, 10(1), p.31.
Bersamin, J., Drio, R., Lacibal, A.L., Manalastas, C., Mendoza, S., Orallo, G.M.D. and Tan, C.T., 2015. Design Process Using Lean Six Sigma to Reduce the Receiving Discrepancy Report of ACE Logistics. In Industrial Engineering, Management Science and Applications 2015 (pp. 665-674). Springer, Berlin, Heidelberg.
Bonner, N.A., Kulangara, N., Nerur, S. and Teng, J.T., 2016. An Empirical Investigation of the Perceived Benefits of Agile Methodologies Using an Innovation-Theoretical model. Journal of Database Management (JDM), 27(3), pp.38-63.
Brioso, X., 2015. Integrating ISO 21500 guidance on project management, lean construction and PMBOK. Procedia Engineering, 123, pp.76-84.
Chaves, M.S., Araújo, C.D., Teixeira, L., Rosa, D., Júnior, I. and Nogueira, C., 2016. A new approach to managing Lessons Learned in PMBoK process groups: the Ballistic 2.0 Model. International Journal of Information Systems and Project Management, 4(1), pp.27-45.
Cheng, J.K., Malik, Z.A. and Sorooshian, S., 2017. Understanding the Interrelationship Between Different Knowledge Areas in PMBOK Through the Development of System Dynamics Model. The Social Sciences, 12(3), pp.473-481.
Considine, C., Crowley, S., Gardner, G., Shannon, C., Kwinn, M.J., Henderson, S.J. and Santamaria, P., 2016, April. Architecting a development and testing plan for the Army’s common operating environment: Applying agile systems of systems development to army network acquisition. In Systems Conference (SysCon), 2016 Annual IEEE (pp. 1-6). IEEE.
Cram, W.A. and Marabelli, M., 2017. Have your cake and eat it too? Simultaneously pursuing the knowledge-sharing benefits of agile and traditional development approaches. Information & Management.
Ferreira, L., Lopes, N., Ávila, P.S., Castro, H., Varela, M.L.R., Putnik, G.D., Martinho, R., Rijo, R., Miranda, I.M. and Cruz-Cunha, M.M., 2017. Virtual Enterprise integration management based on a Meta-enterprise–a PMBoK approach. Procedia Computer Science, 121, pp.1112-1118.
Gonçalves, R.Q., von Wangenheim, C.A.G., Hauck, J.C. and Zanella, A., 2017. An Instructional Feedback Technique for Teaching Project Management Tools Aligned with PMBOK. IEEE Transactions on Education.
Millot, G., Pitois, S., Yan, M., Hovhannisyan, T., Bendahmane, A., Hänsch, T.W. and Picqué, N., 2016. Frequency-agile dual-comb spectroscopy. Nature Photonics, 10(1), p.27.
Nasir, M.H.N.M., Sahibuddin, S., Ahmad, R.B. and Fauzi, S.S.B.M., 2015. How the PMBOK Addresses Critical Success Factors for Software Projects: A Multi-round Delphi Study. JSW, 10(11), pp.1283-1300.
Ohshima, N., 2015. A Study of Concept Structure of PMBOK Based on Graph Theory. Journal on Innovation and Sustainability. RISUS ISSN 2179-3565, 6(1), pp.69-75.
Papadopoulos, G., 2015. Moving from traditional to agile software development methodologies also on large, distributed projects. Procedia-Social and Behavioral Sciences, 175, pp.455-463.
Park, T.W., Kim, K., Rabelo, L. and Lee, G., 2015. An Agile Roadmap for Live, Virtual and Constructive-integrating Training Architecture (LVC-ITA): A Case Study Using a Component Based Integrated Simulation Engine (Doctoral dissertation, University of Central Florida).
Rajkovic, P., Petkovic, I., Milenkovic, A. and Jankovic, D., 2016. Combining Agile and Traditional Methodologies in Medical Information Systems Development Process. In SQAMIA (pp. 65-72).
Rigby, D.K., Sutherland, J. and Takeuchi, H., 2016. Embracing agile. Harvard Business Review, 94(5), pp.40-50.
Rosa, D., Júnior, I.G., Araújo, C., Nogueira, C.D., Chaves, M.S. and Teixeira, L.R., 2016. A New Approach to Managing Lessons Learned in the PMBoK Process Groups: The Ballistic 2.0 Model. International Journal of Information Systems and Project Management (IJISPM).
Serrador, P. and Pinto, J.K., 2015. Does Agile work?—A quantitative analysis of agile project success. International Journal of Project Management, 33(5), pp.1040-1051.
Serrador, P. and Pinto, J.K., 2015. Does Agile work?—A quantitative analysis of agile project success. International Journal of Project Management, 33(5), pp.1040-1051.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.
Spundak, M., 2014. Mixed agile/traditional project management methodology–reality or illusion?. Procedia-Social and Behavioral Sciences, 119, pp.939-948.
Turk, D., France, R. and Rumpe, B., 2014. Limitations of agile software processes. arXiv preprint arXiv:1409.6600.
Varajão, J., Colomo-Palacios, R. and Silva, H., 2017. ISO 21500: 2012 and PMBoK 5 processes in information systems project management. Computer Standards & Interfaces, 50, pp.216-222.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 17 pages

PAY 10 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2020). Project Management Principles. Retrieved from https://myassignmenthelp.com/free-samples/prm701-project-management-principles.

“Project Management Principles.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/prm701-project-management-principles.

My Assignment Help (2020) Project Management Principles [Online]. Available from: https://myassignmenthelp.com/free-samples/prm701-project-management-principles[Accessed 19 December 2021].

My Assignment Help. ‘Project Management Principles’ (My Assignment Help, 2020) accessed 19 December 2021.

My Assignment Help. Project Management Principles [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/prm701-project-management-principles.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

MyAssignmenthelp.com has been providing affordable essay help to thousands of students round the globe. Our essay assistance services can provide solutions and works on essay topics, which are intricate and rare. 200K + students trust us , not without a reason. It is because every assignment and essays have been crafted to precision, edited on various parameters by known essayists and finally proofread and referenced properly to give essays that drive envy

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog