Fundraising For Charity
2 Downloads8 Pages / 1,940 Words
Question:
Discuss about the Fundraising For Charity.
Answer:
A Fund Raising Event By A Company For A Charity Organisation
Introduction
The project selected is the fund raising event by a company for a charity organization. The project is so chosen that the new and multi-national companies are increasingly involving in philanthropy. As a part of that the companies are more involved in generating the funds for the self-running charitable trusts as well as increasingly for supporting the organizations that work for the charity.
The project involves the activities and tasks to conduct an event with an objective to raise some fund and forward the fund to an organization that works for charity and social cause (Cattani et al., 2011). The project is to be conducted by building a team to plan and organize the event. The project needs to figure out the budget and finances for the event. The budget is expected to be invested by the company initially. And the budget spent would be collected from the overall fund raised by the event. The budget is expected to be smaller amount compared to the fund raised.
The project has to be taken care exclusively by the company. So, the company is accountable and responsible for the entire event and the fund that is going to be raised for the charity organization. The company is expected to explore multiple options to generate or raise the fund for the charity organization. However, finally, only one option has to be selected to implement. So, in this project, the selection of the viable and most potential options among all the other options is done with the help of the priority matrix. Eventually, the same option is going to be implemented. The project planning and implementation is developed for the finally selected option to raise the fund for the charity organization (Lock, 2011).
Scope
Objective
The scope of the project is to collect the money, raised from the event and forward the fund to the organization that is pre-selected and that works for charity. The scope of the project does not include the branding of the company and profit of the company, though the branding and reputation may be increased for the company after the event. The scope does not include how the money is spent by the charity organisation (Wysocki, Robert, 2013). The objective of the project is to raise the fund for the charity organization, with no intention and process intended to gain the profit from the event.
Deliverables
The deliverables of the project are a detailed activities and tasks for the event to be conducted, after the selection of the appropriate event for charity organization.
Milestones
Development of the plan
Making all the preparations for the event
Completion of the event
Calculation of the fund raised
Submitting the fund raised to the charity organisation
Technical Requirements
The technical requirements of the project are the following.
A computer
Infrastructure needed to conduct the event
Detailed specifications of the items presented in the auction
Limits and Exclusions
The limits and exclusions include the acceptance of the price, if it is within the pre-defined price by the company without losses. Other products and items are excluded, except for the auction items.
Review with Customers
Customer reviews are to be collected with the questionnaire posted in the home page of the company website. In addition, a function is enabled to add the review of the event and project by the customer.
Priorities
There are multiple ways to raise the fund for the charity. Since it is a good cause, public and people are inclined to involve and spend good amount of money in such events and projects. Eventually, there are many ways explored and implemented by the individuals, the charity organizations and the companies that support the charity organizations. Companies find many ways to conduct the events, as they already have good access to the public, in the form of their customers. The events can be conducted either by the direct organisation or even by outsourcing the projects to them. Here, in this instance, the company is going to conduct the event directly. The company is going to spend for the event and the human resources needed for the event are directly taken from within the company, by looking for the volunteers (Stellman et al., 2005).
Most of the possible ways are explored and then the best way to raise the fund for the charity is going to be selected. Each of the way of raising the fund is explored, in terms of time, performance and cost. The constraint is considered to ensure the viability in terms of time taken to implement the entire event. The performance is considered in terms of how well it can be enhanced. The cost is considered to ensure whether the project can be accepted or not.
The selected event is going to be planned for the viability.
The basic priorities of the fundraising by the company are selected to be the following.
Hosting a street carnival
Organizing the competition
Raffle selling
Auction
Organizing a dance-a-thon
Imprisoning a celebrity
Options
Time
Performance
Cost
Hosting a street carnival
High
Medium
High
Organizing the competition
High
High
High
Raffle Selling
Medium
Medium
High
Auction
Less
High
Less
Organizing a dance-a-thon
High
High
High
Imprisoning a celebrity
High
High
High
Table: Priority Matrix
Time
Scope
Cost
Constraint
x
Enhance
x
Accept
x
There are total six options selected to raise the fund. Among all these options, Auction is selected as it can be the most potential option for raising the fund. Based on the company and its functions, employees and the products that it handles, the company has decided to go with the auction. The option auction is selected, as it is going to take less time as all it needs is a few hours in a day. It is going to give much higher performance, as it involves intensive and high value items in the auction. It is going to take less cost, as the event needs the transport of the items, inviting the guests and the participation of the volunteer employees from the same company.
Work Breakdown Structure
Planning of the event
Setting the objective
Identifying the audience
Deciding the type of fund raiser
Identifying the deadline
Studying the other similar fundraising events that run successful
Create minute to minute activities of the event
Build up a team
Look and seek out for volunteers in the company
Delegate the accountability, responsibility and authority
Split up the overall tasks for the event
Decide the professionals needed at the site
Estimate the Budget
Budget for hiring the site for the event
Budget for logistics
Budget for amenities
Budget for professionals hired out from company
Arrangement of the logistics
Decide the date and time for the event
Find location suitable
Develop the schedule
Negotiate for transport and finalize
Plan for follow up
Inform the volunteers
Conduct an Event
Take all the volunteers according to the schedule
Take the infrastructure and other material needed
Conduct the tasks and activities
Post event procedures
Clear the payments for logistics
Clear all the bills and dues for services
Clear the site
Payoff for the services
Fundraise
Calculate the total amount generated
Subtract the budget spent for the event
Release the final fund raised amount to the charity organization
Closing the project
Relieve the volunteers
Relieve the operations
Submit the final report of the project
Cost Estimation
Task Name
Duration
Start
Finish
Cost
Planning the event
2 days
Mon 15-08-16
Tue 16-08-16
$100
Setting the objective
1 day
Mon 15-08-16
Mon 15-08-16
Identifying the audience
1 day
Mon 15-08-16
Mon 15-08-16
Studying the similar fundraising events
1 day
Tue 16-08-16
Tue 16-08-16
Creating minute to minute plan
1 day
Tue 16-08-16
Tue 16-08-16
Building a team
2 days
Wed 17-08-16
Thu 18-08-16
$100
Look for volunteers
1 day
Wed 17-08-16
Wed 17-08-16
Delegating the responsibilities
1 day
Wed 17-08-16
Wed 17-08-16
Splitting the tasks
1 day
Thu 18-08-16
Thu 18-08-16
Deciding professionals at site
1 day
Thu 18-08-16
Thu 18-08-16
Estimating the budget
1 day
Fri 19-08-16
Fri 19-08-16
$100
Budget to hire the site
1 day
Fri 19-08-16
Fri 19-08-16
Budget for logistics
1 day
Fri 19-08-16
Fri 19-08-16
Budget for amenities
1 day
Fri 19-08-16
Fri 19-08-16
Budget for professionals
1 day
Fri 19-08-16
Fri 19-08-16
Arrangement of the logistics
5 days
Mon 22-08-16
Fri 26-08-16
$300
Deciding the date and time
1 day
Mon 22-08-16
Mon 22-08-16
Finding the location
1 day
Tue 23-08-16
Tue 23-08-16
Developing the schedule
1 day
Wed 24-08-16
Wed 24-08-16
Negotiating the transport
1 day
Thu 25-08-16
Thu 25-08-16
Planning the follow up
1 day
Fri 26-08-16
Fri 26-08-16
Inform the volunteers
1 day
Fri 26-08-16
Fri 26-08-16
Conducting the event
1 day?
Mon 29-08-16
Mon 29-08-16
$5500
Taking the volunteers
1 day
Mon 29-08-16
Mon 29-08-16
$1000
Taking the infrastructure
1 day
Mon 29-08-16
Mon 29-08-16
$500
Conducting the tasks
1 day
Mon 29-08-16
Mon 29-08-16
$4000
Post event procedures
1 day?
Tue 30-08-16
Tue 30-08-16
$300
Clearing the payments for logistics
1 day
Tue 30-08-16
Tue 30-08-16
Clearing all the dues and bills
1 day
Tue 30-08-16
Tue 30-08-16
Clearing the site
1 day
Tue 30-08-16
Tue 30-08-16
Payoff for other services
1 day
Tue 30-08-16
Tue 30-08-16
Fundraise
1 day?
Wed 31-08-16
Wed 31-08-16
$300
Calculating the amount generated
1 day
Wed 31-08-16
Wed 31-08-16
Subtracting the budget spent
1 day
Wed 31-08-16
Wed 31-08-16
Releasing the final fund
1 day
Wed 31-08-16
Wed 31-08-16
Closing the project
1 day?
Thu 01-09-16
Thu 01-09-16
$500
Relieve the volunteers
1 day
Thu 01-09-16
Thu 01-09-16
Relieve the operations
1 day
Thu 01-09-16
Thu 01-09-16
Submit the final report
1 day
Thu 01-09-16
Thu 01-09-16
Figure: Cost estimation with top-down approach, Apportion method
Conclusion
The project has been developed with an objective of raising the fund for the charity organization. The charity organisation is expected to be selected already, before the commencement of the project. So, the entire project has been developed for planning and implementing the project of fundraising for the charity organization by the company.
References
Cattani, G., Ferriani, S., Frederiksen, L. and Florian, T. (2011) Project-Based Organizing and Strategic Management, Advances in Strategic Management, Vol 28, Emerald,
David C. I, Gareis. R. (2006). Global Project Management Handbook. McGraw-Hill Professional
Lock. D. (2007) Project Management (9th ed.) Gower Publishing, Ltd.
Epstein, G. S. (2008). Herd and network effects in migration decision-making. Journal of Ethnic and Migration Studies, 34(4), 567-583.
Harrison, F. L. Lock. D. (2004). Advanced project management: a structured approach. Gower Publishing, Ltd.
Phillips. J., (2003). PMP Project Management Professional Study Guide. McGraw-Hill Professional, 2003.
Stevens. M. (2002). Project Management Pathways. Association for Project Management. APM Publishing Limited
Paul. D. C. et al (2005) The right projects done right! John Wiley and Sons
Stellman, Andrew; Greene, Jennifer (2005).Applied Software Project Management. O’Reilly Media
Wysocki, Robert K (2013). Effective Project Management: Traditional, Adaptive, Extreme (Seventh Edition). John Wiley & Sons.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 8 pages
PAY 5 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2017). Fundraising For Charity. Retrieved from https://myassignmenthelp.com/free-samples/fundraising-for-charity.
“Fundraising For Charity.” My Assignment Help, 2017, https://myassignmenthelp.com/free-samples/fundraising-for-charity.
My Assignment Help (2017) Fundraising For Charity [Online]. Available from: https://myassignmenthelp.com/free-samples/fundraising-for-charity[Accessed 19 December 2021].
My Assignment Help. ‘Fundraising For Charity’ (My Assignment Help, 2017)
My Assignment Help. Fundraising For Charity [Internet]. My Assignment Help. 2017 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/fundraising-for-charity.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com is one of the noted service providers that deliver essay help. We provide tailored essay assistance to make sure that student gets online essay help exactly in the way they want it to be written. We at MyAssigemnthelp.com have built teams of consultants, who readily attend every query related to help me writing my essay. We provide essay writing help in forms of tips and steps in order o assist students with tough essay assignments.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …