Question:
1.Draw an activity-on-arrow (AON) diagram for these 15 project tasks (A to O). Calculate, display and clearly label on the diagram, the earliest and latest start and finish times and float of each task? Clearly show Workings
2. What effect will each of the following changes (when considered separately) have on the critical path(s) and the completion time of the overall project? Give reasons for your answer.
Activity D is delayed by 2 weeks.
Activity G is completed in 8 weeks.
3. Clearly show how the project network you have drawn in (b) above needs to be amended to represent the logical constraint that activity O cannot start until at least 4 days after activity M has finished. How are the overall project completion time and critical path(s) affected if this condition is imposed?
Answer:
1.Project Plan
Task Name
Completion time
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Free Slack
Predecessors
Activity
19 wks
Thu 3/8/18
Wed 7/18/18
Thu 3/8/18
Wed 7/18/18
Thu 3/8/18
Wed 7/18/18
0 wks
A
3 wks
Thu 3/8/18
Wed 3/28/18
Thu 3/8/18
Wed 3/28/18
Thu 3/8/18
Wed 3/28/18
0 wks
B
4 wks
Thu 3/8/18
Wed 4/4/18
Thu 3/8/18
Wed 4/4/18
Thu 3/15/18
Wed 4/11/18
0 wks
C
4 wks
Thu 3/8/18
Wed 4/4/18
Thu 3/8/18
Wed 4/4/18
Thu 3/15/18
Wed 4/11/18
0 wks
D
4 wks
Thu 3/29/18
Wed 4/25/18
Thu 3/29/18
Wed 4/25/18
Thu 3/29/18
Wed 4/25/18
0 wks
1
E
4 wks
Thu 3/29/18
Wed 4/25/18
Thu 3/29/18
Wed 4/25/18
Thu 5/31/18
Wed 6/27/18
9 wks
1
F
2 wks
Thu 4/5/18
Wed 4/18/18
Thu 4/5/18
Wed 4/18/18
Thu 4/12/18
Wed 4/25/18
1 wk
2
G
3 wks
Thu 4/5/18
Wed 4/25/18
Thu 4/5/18
Wed 4/25/18
Thu 5/3/18
Wed 5/23/18
4 wks
2
H
4 wks
Thu 4/5/18
Wed 5/2/18
Thu 4/5/18
Wed 5/2/18
Thu 4/26/18
Wed 5/23/18
2 wks
2
I
6 wks
Thu 4/5/18
Wed 5/16/18
Thu 4/5/18
Wed 5/16/18
Thu 4/12/18
Wed 5/23/18
0 wks
3
J
4 wks
Thu 4/5/18
Wed 5/2/18
Thu 4/5/18
Wed 5/2/18
Thu 5/3/18
Wed 5/30/18
0 wks
3
K
4 wks
Thu 4/26/18
Wed 5/23/18
Thu 4/26/18
Wed 5/23/18
Thu 4/26/18
Wed 5/23/18
0 wks
4,6
L
5 wks
Thu 5/24/18
Wed 6/27/18
Thu 5/24/18
Wed 6/27/18
Thu 5/24/18
Wed 6/27/18
0 wks
7,11
M
5 wks
Thu 5/17/18
Wed 6/20/18
Thu 5/17/18
Wed 6/20/18
Thu 5/24/18
Wed 6/27/18
1 wk
8,9
N
4 wks
Thu 5/3/18
Wed 5/30/18
Thu 5/3/18
Wed 5/30/18
Thu 5/31/18
Wed 6/27/18
4 wks
10
O
3 wks
Thu 6/28/18
Wed 7/18/18
Thu 6/28/18
Wed 7/18/18
Thu 6/28/18
Wed 7/18/18
0 wks
5,12,13,14
Arrow On Network Diagram illustrating forward pass and backward pass calculation
Critical Path initially
2.Project Plan
2.1 Task D gets delayed to 2 weeks. So, overall project completion time changes from 19 weeks to 21 weeks.
Task Name
Completion time
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Free Slack
Predecessors
Activity
21 wks
Thu 08-03-18
Wed 01-08-18
Thu 08-03-18
Wed 01-08-18
Thu 08-03-18
Wed 01-08-18
0 wks
A
3 wks
Thu 08-03-18
Wed 28-03-18
Thu 08-03-18
Wed 28-03-18
Thu 08-03-18
Wed 28-03-18
0 wks
B
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Thu 29-03-18
Wed 25-04-18
0 wks
C
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Thu 29-03-18
Wed 25-04-18
0 wks
D
6 wks
Thu 29-03-18
Wed 09-05-18
Thu 29-03-18
Wed 09-05-18
Thu 29-03-18
Wed 09-05-18
0 wks
1
E
4 wks
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
Thu 14-06-18
Wed 11-07-18
11 wks
1
F
2 wks
Thu 05-04-18
Wed 18-04-18
Thu 05-04-18
Wed 18-04-18
Thu 26-04-18
Wed 09-05-18
3 wks
2
G
3 wks
Thu 05-04-18
Wed 25-04-18
Thu 05-04-18
Wed 25-04-18
Thu 17-05-18
Wed 06-06-18
6 wks
2
H
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Thu 10-05-18
Wed 06-06-18
2 wks
2
I
6 wks
Thu 05-04-18
Wed 16-05-18
Thu 05-04-18
Wed 16-05-18
Thu 26-04-18
Wed 06-06-18
0 wks
3
J
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Thu 17-05-18
Wed 13-06-18
0 wks
3
K
4 wks
Thu 10-05-18
Wed 06-06-18
Thu 10-05-18
Wed 06-06-18
Thu 10-05-18
Wed 06-06-18
0 wks
4,6
L
5 wks
Thu 07-06-18
Wed 11-07-18
Thu 07-06-18
Wed 11-07-18
Thu 07-06-18
Wed 11-07-18
0 wks
7,11
M
5 wks
Thu 17-05-18
Wed 20-06-18
Thu 17-05-18
Wed 20-06-18
Thu 07-06-18
Wed 11-07-18
3 wks
8,9
N
4 wks
Thu 03-05-18
Wed 30-05-18
Thu 03-05-18
Wed 30-05-18
Thu 14-06-18
Wed 11-07-18
6 wks
10
O
3 wks
Thu 12-07-18
Wed 01-08-18
Thu 12-07-18
Wed 01-08-18
Thu 12-07-18
Wed 01-08-18
0 wks
5,12,13,14
2.1 Change in Critical Path
2. Project Plan
2.2 Task G gets completed in 8 weeks. So, overall project completion time changes from 19 weeks to 20 weeks.
Task Name
Completion time
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Free Slack
Predecessors
Activity
20 wks
Thu 08-03-18
Wed 25-07-18
Thu 08-03-18
Wed 25-07-18
Thu 08-03-18
Wed 25-07-18
0 wks
A
3 wks
Thu 08-03-18
Wed 28-03-18
Thu 08-03-18
Wed 28-03-18
Thu 15-03-18
Wed 04-04-18
0 wks
B
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
0 wks
C
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Thu 22-03-18
Wed 18-04-18
0 wks
D
4 wks
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
Thu 05-04-18
Wed 02-05-18
0 wks
1
E
4 wks
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
Thu 07-06-18
Wed 04-07-18
10 wks
1
F
2 wks
Thu 05-04-18
Wed 18-04-18
Thu 05-04-18
Wed 18-04-18
Thu 19-04-18
Wed 02-05-18
1 wk
2
G
8 wks
Thu 05-04-18
Wed 30-05-18
Thu 05-04-18
Wed 30-05-18
Thu 05-04-18
Wed 30-05-18
0 wks
2
H
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Thu 03-05-18
Wed 30-05-18
2 wks
2
I
6 wks
Thu 05-04-18
Wed 16-05-18
Thu 05-04-18
Wed 16-05-18
Thu 19-04-18
Wed 30-05-18
0 wks
3
J
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Thu 10-05-18
Wed 06-06-18
0 wks
3
K
4 wks
Thu 26-04-18
Wed 23-05-18
Thu 26-04-18
Wed 23-05-18
Thu 03-05-18
Wed 30-05-18
1 wk
4,6
L
5 wks
Thu 31-05-18
Wed 04-07-18
Thu 31-05-18
Wed 04-07-18
Thu 31-05-18
Wed 04-07-18
0 wks
7,11
M
5 wks
Thu 17-05-18
Wed 20-06-18
Thu 17-05-18
Wed 20-06-18
Thu 31-05-18
Wed 04-07-18
2 wks
8,9
N
4 wks
Thu 03-05-18
Wed 30-05-18
Thu 03-05-18
Wed 30-05-18
Thu 07-06-18
Wed 04-07-18
5 wks
10
O
3 wks
Thu 05-07-18
Wed 25-07-18
Thu 05-07-18
Wed 25-07-18
Thu 05-07-18
Wed 25-07-18
0 wks
5,12,13,14
2.2 Change in Critical Path
3.Project Plan
The activity O cannot get started until at least 4 days after the activity M has finished. Therefore, the completion time for activity O is 5.4 weeks. The overall completion time of the project does not get affected.
Task Name
Duration
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Free Slack
Predecessors
Activity
19 wks
Thu 08-03-18
Wed 18-07-18
Thu 08-03-18
Wed 18-07-18
Thu 08-03-18
Wed 18-07-18
0 wks
A
3 wks
Thu 08-03-18
Wed 28-03-18
Thu 08-03-18
Wed 28-03-18
Thu 08-03-18
Wed 28-03-18
0 wks
B
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Thu 15-03-18
Wed 11-04-18
0 wks
C
4 wks
Thu 08-03-18
Wed 04-04-18
Thu 08-03-18
Wed 04-04-18
Tue 13-03-18
Mon 09-04-18
0 wks
D
4 wks
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
0 wks
1
E
4 wks
Thu 29-03-18
Wed 25-04-18
Thu 29-03-18
Wed 25-04-18
Thu 31-05-18
Wed 27-06-18
9 wks
1
F
2 wks
Thu 05-04-18
Wed 18-04-18
Thu 05-04-18
Wed 18-04-18
Thu 12-04-18
Wed 25-04-18
1 wk
2
G
3 wks
Thu 05-04-18
Wed 25-04-18
Thu 05-04-18
Wed 25-04-18
Thu 03-05-18
Wed 23-05-18
4 wks
2
H
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Tue 24-04-18
Mon 21-05-18
2 wks
2
I
6 wks
Thu 05-04-18
Wed 16-05-18
Thu 05-04-18
Wed 16-05-18
Tue 10-04-18
Mon 21-05-18
0 wks
3
J
4 wks
Thu 05-04-18
Wed 02-05-18
Thu 05-04-18
Wed 02-05-18
Thu 03-05-18
Wed 30-05-18
0 wks
3
K
4 wks
Thu 26-04-18
Wed 23-05-18
Thu 26-04-18
Wed 23-05-18
Thu 26-04-18
Wed 23-05-18
0 wks
4,6
L
5 wks
Thu 24-05-18
Wed 27-06-18
Thu 24-05-18
Wed 27-06-18
Thu 24-05-18
Wed 27-06-18
0 wks
7,11
M
5.4 wks
Thu 17-05-18
Fri 22-06-18
Thu 17-05-18
Fri 22-06-18
Tue 22-05-18
Wed 27-06-18
0.6 wks
8,9
N
4 wks
Thu 03-05-18
Wed 30-05-18
Thu 03-05-18
Wed 30-05-18
Thu 31-05-18
Wed 27-06-18
4 wks
10
O
3 wks
Thu 28-06-18
Wed 18-07-18
Thu 28-06-18
Wed 18-07-18
Thu 28-06-18
Wed 18-07-18
0 wks
5,12,13,14
Change in Critical Path
References:
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Pinto, J.K., 2015. Project management: achieving competitive advantage. Prentice Hall.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 7 pages
PAY 5 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2020). Project Management. Retrieved from https://myassignmenthelp.com/free-samples/bg007-project-management.
“Project Management.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/bg007-project-management.
My Assignment Help (2020) Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/bg007-project-management[Accessed 19 December 2021].
My Assignment Help. ‘Project Management’ (My Assignment Help, 2020)
My Assignment Help. Project Management [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/bg007-project-management.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
Are you pursuing a PhD course program? It is common among the research scholars to struggle with their dissertation topics at the initial stage. In such a situation, getting assistance from the experts at MyAssignmenthelp.com is a wise decision. The service offers you all the necessary support on the dissertation structure and the dissertation methodology. Unfortunately, most students are perplexed about the exact format of the dissertation. However, academic experts at MyAssignmenthelp.com are ready to provide you with dissertation assistance with relevant content and format.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More